Completion Date: August 2014
Client: Consolidated Edison Development (CED)
Tulare Valley, California
White River 2 Solar project is a 26.6MWDC solar photovoltaic, grid connected power generation facility. This project was completed in 10 months.
Ryan’s responsibilities comprised full engineering, procurement and construction of the entire system including procurement of electrical equipment, preparation of the site involving management of all project grading and trenching. Ryan also installed the support structures, module racking system, modules, inverters, DC wiring, AC power cables, with the associated collection equipment and all electrical systems for the entire project involving module connections and inverter installation. The Ryan team designed and optimized the project processes, installation and the 34.5kV-11.5Kv substation.
Engineering, Procurement and Construction of a 9.95MWac/13.44MWdc Solar Project. Scope includes installation of 685W-695W PV modules, support structures, tracker system; DC-AC power conversion equipment; DC...
Engineering, Procurement and Construction of an 80MWac/106.8MWdc Solar, 69kV/34.5kV Substation and 69kV Switching Station. Scope includes installation of 540W PV modules, support structures, tracker racking...
Engineering, Procurement and Construction of a 100MWac/131.67MWdc Solar Project. Scope includes installation of 540W PV modules, support structures, tracker racking system; DC-AC power conversion equipment;...
The quality of our people is the cornerstone of our ability to serve our clients. The Ryan Company, Inc. is comprised of the best and the brightest in the industry. Visit our Careers page and find out more!
CareersSend us a message to get in touch with us for any comments, concerns, or questions you may have.
Contact Us