Completion Date: February 2022
Location: Washoe, Nevada
Client: NextEra Energy
Juno Beach, Flordia
Construction of a new 345KV Substation and 25MW/100MWh Battery Energy Storage.
Scope included 345/34.5kV Substation, 345kV Gen-tie span, 25MW BESS System with 12 battery container & 8 integrated invertors, initial site preparation, foundations, site fencing, station grounding, control and power conduit and cables, steel structures, HV and LV electrical equipment (transformer, breakers, switches, capacitors and disconnects) control building with SEL Relay Panels, rigid bus and jumper overhead system and all testing and commissioning services.
Construction of a new 100MW/400MWh Battery Energy Storage System and Retrofit of existing 345kV Substation. Scope included 100MW BESS System with 93 battery container &...
Construction of a new 13MW/49.4MWh Battery Energy Storage System and Retrofit of existing 345kV Substation. Scope included 13MW BESS System with 24 battery container &...
Construction of a new 88MW/302MWh Battery Energy Storage System, New 230/34.5kV Substation, Retrofit existing 230kV Substation and New 230kV Transmission Line. Scope included 88MW BESS...